“Plan ahead” as bridgeworks return

IN A MAJOR change of plan, VicRoads has announced with just four days’ advance notice that the resurfacing works on the bridge will commence next Monday, February 11 and are scheduled to take place for the full week in both daytime and night-time including the morning peak period.

Daytime works are scheduled to take place between 7am and 5pm from Monday, February 11 to Saturday, February 16.

Night-time works are scheduled to take place between 8pm and 5am from Tuesday, February 12 to Monday, February 18.

The suddenness of these works and the announcement of both day and night lane closures may come as a bit of a shock, when the Diary recently asked VicRoads about any further lane closures, Stephane Hinkeesing, Manager Structures Metro said:

“Over the coming weeks, we’ll be finalising our works including new asphalting on the bridge and permanent line marking.

“During these works, there may be some overnight temporary lane closures.”

The new update advises that during the above times there will be lane closures on the bridge; however traffic flow will be maintained with on-site traffic management, although it is unclear how many lanes will be open.

The latest email update also states:

“Works can only proceed under favourable weather conditions and can be impacted by rain, cold or excessive heat.

Contingency dates have been included in case of unfavourable weather.”

This would indicate — assuming all goes well — road users in Warrandyte may not need to suffer through a full week of lane closures.

But with peak time traffic still backing up, it is possible that any lane closures are going to have an adverse effect on already congested Warrandyte roads.

Take heed at VicRoads advice, plan ahead and assume the bridge is out of order for the second full week of February.

November roadworks

UPDATE: Monday November 19

An overnight lane closure has been scheduled on the Warrandyte Bridge between 8pm on Monday November 19 and 5am on Tuesday November 20 – with traffic allowed to cross the bridge, using only 1 (one) lane, under traffic management.

If you are travelling across the Warrandyte Bridge or around the area between these times, please me mindful there may be delays to your journey.

These works are advertised to allow the relocation of temporary safety barriers.

The November/December update also indicates roadworks to expand the bus top on the roundabout are also due to occur in the near future –  these works will allow articulated (bendy) busses to use the Warrandyte Bridge  bus stop, the Diary is looking into this as we are unaware of any plans to introduce “bendy busses” to the 906 bus route.

The bridge bus stop will be closed when these roadworks occur.

When these works take place, the bus stop outside the Warrandyte Library will serve as the start point for the 906.

The Warrandyte Diary will update this story as more details become available.

***************************************************************************************************************

[previous story continues below]

With last weeks overnight closures cancelled due to the wet weather, VicRoads today announced the next string of bridge and lane closures starting this Sunday.

On Sunday November 11, the bridge will be completely closed to traffic overnight, from 8pm Sunday to 5am Monday morning.

As with previous bridge closures, pedestrians and bicycles will still be able to cross the bridge, under the guidance of traffic management.

On Monday November 12, the bridge, and the roads around it, will be reduced to one lane, under traffic management between 8pm and 5am the next morning.

On Tuesday November 13, the bridge and surrounding roads will again be educed to one lane, under traffic management between 8pm and 5am the next morning.

As with the planned closures on November 7 and 8, these works are to facilitate asphalting and line marking – let’s hope the weather is more agreeable this time.

 

Warrandyte bridgeworks update

Bridge reduced to one lane overnight tonight to facilitate lane switch

AFTER a successful concrete pour, VicRoads have today announced the Warrandyte Bridge lane swap will happen overnight between 10pm, Wednesday July 11 and 5am, Thursday July 12.

Contraflow and traffic management will be in place to ensure traffic is still able to move across the Bridge overnight.

When completed, northbound traffic will use the new section of the bridge.

Southbound traffic will continue to use the current upstream lane.

This will allow VicRoads contractors VEC to work on the middle section of the bridge.

Pedestrian access will remain on the upstream path and the north bank pedestrian crossing will remain in place until bridgeworks are completed.

The Diary will keep across this story and report here if there are any changes to the current bridgeworks plan.