Warrandyte faces Ring Road as Bulleen says NO to NELA

RESIDENTS FROM across Manningham descended on the Manningham Council Function room on September 25 to hear and be heard about the proposed options for the North East Link toll road which is planned to be built in the next few years.

A very vocal contingent of Bulleen residents was in attendance to show opposition to Option A which travels through their part of Manningham leaving a small group from Warrandyte drowned out by the noise from the Option A objectors.

Manningham Councillor Paul McLeish is particularly concerned the huge opposition from Bulleen residents opens up Warrandyte as the “path of least resistance”.

“If the people of Warrandyte, Park Orchards, Donvale and Wonga Park don’t raise their voice, they could end up with a very poor outcome … we will end up having Warrandyte, North Warrandyte and West Warrandyte, cut in half by a major road bridge from Beasley’s through to Stinton’s Road — taking out Aumann’s, the Baseball Park, Crystal Brook, Stinton’s Football ground and Park Orchards BMX club; wiping out millions of dollars of community facilities,” he told the Diary.

Despite following different routes in the North, both Options B and C follow the same route through the southwest of Warrandyte while Option D takes a 40km journey through Kangaroo Ground and Lilydale.

With vocal opposition for Option A and Nillumbik Council expressing their opposition to both Options C and D, odds are firming in favour of Option B, but the effect of this road on the existing network is unclear.

“I think Warrandyte is in significant risk of increased traffic because freeways induce traffic and the limited number of interchanges means that traffic north of Warrandyte will be pulled towards the Reynolds Road interchange and the Reynolds Road interchange will be a magnet for traffic from across the east, for 360 degrees around it — it will be a magnet for traffic and that traffic will seek to avoid the tolls for the tunnels so you will see traffic pouring up Springvale Road and into the Reynolds Road interchange, pouring out of North Croydon into Reynolds Road, a significant increase in pollution, they are terrible outcomes for our community,” said Cr McLeish.

Spokesperson for the Warrandyte Community Association (WCA), Doug Seymour told the Diary they have provided a range of questions to NELA, and says that to date they have had no reply.

“There seems to be an imbalance between community groups providing valuable questions to help the Authority to focus their risk management processes while NELA [North East Link Authority] is not able or is unwilling to provide the meaningful feedback required for Warrandyte…NELA is not providing the data and information for us to understand the scale of the impact of Corridors B or C,” Mr Seymour said.

Member for Warrandyte, Ryan Smith is concerned with lack of detail provided by NELA, who has “only been prepared to give limited information to our community.”

“Potential impacts include a major interchange at Tindals Road, the loss of Stintons Reserve and emissions being expelled from the planned tunnels, which will collect in the valley — this is on top of the impact on local wildlife during the decade long construction period.

“It is important that the severity of these impacts are accurately communicated to residents so they can give informed feedback to the government,” he said.

Following the public forum, Manningham Council discussed the framework of its submission to NELA. During the meeting, several motions were debated with two being adopted. Councillor Paula Piccinini from Heide Ward successfully passed a motion for Council to oppose Option A, however Cr McLeish was unsuccessful in his amendment to offer the same unqualified objection to options B and C.

“All of the effects that are proposed in Bulleen are similarly proposed in Mullum Mullum [ward]… these areas are no less sensitive than the Bolin Bolin area in Bulleen, I cannot see why we should seek to nominate losers in this proposal by selectively picking a winner in Bulleen by saying it should not have a route through it, surely we as a council can do what we are elected to do, to stand on the principals we espouse for this particular project, to protect the amenity of all residents of our city, not just the selected residents who are impacted in Bulleen, if we are going to speak against these attributes then surely that is a motion to speak against the entire proposal”, he told Council.

Manningham Mayor, Cr Michelle Kleinert told the Diary that the aim of the motion is to highlight the preliminary local issues, opportunities and concerns to NELA.

“With three of the four proposed route options going through Manningham but very limited information available to make a solid analysis and evaluation of each route. Council is also requesting NELA undertake and provide further technical information and a detailed impact assessment of each of the four corridor options, and to further engage with the community and Council on the matter”.

Cr Kleinert successfully proposed to survey of all Manningham residents to inform Council of all residents’ views, not merely the vocal activists from the Bulleen area.

“The survey will be distributed in October to hear from all members of our community that could be affected, should route option A, B or C be NELA and the State Government’s preferred route.

“The results of the survey will be shared with the Manningham community and passed on to NELA to incorporate into their engagement,” she said.

Councillor Anna Chen noted that she supported the motion to object to Option A because of the passionate representation from the Bulleen community at the Manningham forum.

“You can hear the voices from the community,” she said to councillors.

Councillor McLeish told the Diary he was disappointed that his amendment to Cr Piccinini’s motion was unsuccessful, however “I will continue to protect Warrandyte and its community”, he said.

From the outset Corridor A has seemed to be the preferred route, but significant political, municipal and community pressure is building for Corridor B to be selected.

We need to be prepared for what this means for Warrandyte.

 

North East Link Forum

A group of residents effected by routes B and C have joined together to form the North East Link Forum (NELF), the group have also submitted a formal concerns paper to NELA.

This group is deeply concerned with the impact Corridors B and/or C will have on Warrandyte, Park Orchards and Donvale if either of these Corridors is selected.

If you are interested in what NELF are doing, you can find them on Facebook.

North East Link planning hots up

ACTIVITY IS RAMPING up in the planning for the North East Link, and the route to be chosen is by far the most contentious issue.

North East Link Authority (NELA)

NELA has confirmed their process of consultation will commence in July/August.

Their current investigations are concentrating on geotechnical testing and analysis.

Their website has a short video on the current program of drilling to take soil samples from 24 sites.

Geotechnical study sites (North East Link Authority website)

Whilst the line of drillings to the west of Warrandyte follows the expected path of the central route past Beasley’s Nursery, there is one curious drilling location shown in Warrandyte, south of the river around the Stonehouse Café area.

Katie Hall, Corporate Communications and Media Manager North East Link Authority, told the Diary “the drill locations on the video map are indicative of where drilling will take place but are not exact.

“Where the rigs are set up depends on where there is a suitable location such as a VicRoads reservation, and where we are missing information regarding the soil and rock profiles,” she said.

The current investigations will look at the suitability of tunnelling, cut and fill, gradients, vegetation, environmental and socioeconomic considerations.

NELA will then identify several corridors.

Each of the identified corridors will have a full analysis of the positives and negatives for each.

This process will not select a route for the NE Link; it is a broad corridor identification process only.

After the corridors have been identified, the first full round of public consultation by NELA will commence.

The consultations will allow the public to have input into the corridors identified and to make submissions with respect to their suitability.

Nillumbik Pro-Active Landowners (PALs)

The PALs group conducted a survey via their Facebook page, this survey received 146 responses.

47% of the responders were from Kangaroo Ground while only 1% were from North Warrandyte.

The overwhelming majority (94%) of respondents supported the North East Link with only 5% saying they did not support it.

While 70% objected to the road being built in Nillumbik, with 25% saying they approved of a Green Wedge route, and 65% supporting the link being mainly tunnel (12% against).

Spokesman for the PALs group, Max Parsons, told the Diary PALs will be working to ensure NELA understand, acknowledge and appreciate the importance of the Green Wedge to the residents and landowners in Nillumbik, as well as its state and national significance, Mr Parsons also stressed the importance of financial compensation for landowners.

“With a determined view to the primacy of human life in relation to bush fire risk, the loss of vegetation and Green Wedge areas, the dissection of and disruption to existing communities and the isolation of native fauna must all be factored into the equation to select an appropriate route for the North East Link.

“Should the North East Link proceed, affected landowners must receive appropriate market-based compensation for any acquired land or adjoining affected properties,” he said.

Warrandyte Community Association (WCA)

The WCA has expressed concern Banyule Council and residents are mounting a well-organised campaign advocating the Central Option to the west of Warrandyte as preferable to the shorter route running down to andunder the Banyule river flats to join the Eastern Freeway at Bulleen.

Convenor of the Warrandyte Community Association subcommittee working on this issue, Carli Lange-Boutle, feels the action in Banyule could have serious impact on Warrandyte.

“The Government plans to start construction on the Link in 2019 and community groups and Councils along the various routes are linking up and preparing to argue against a route through their communities,” she said

The WCA understands the public will have only six weeks in which to respond to the NELA Route Options paper, planned for issue in late July so the research needed to lodge an objection needs to begin now.

The WCA is alarmed at the potential impact of the Greensborough–Ringwood route.

The borehole location figure on the NELA website confirms the Authority is considering an alignment parallel to the high voltage powerline easements running from St Helena to Ringwood, crossing or passing under the Yarra River near Target Road in Warrandyte.

At 19 km long, this route would be over twice the length of the Banyule route and unless extensive tunnelling is used, it would impact the Diamond and Mullum Mullum Creeks, as well as the Yarra River.

Mrs Lange-Boutle says, “Access ramps at Reynolds Road near Springvale Rd seem likely for this route option and this could generate serious traffic volumes for Yarra Street Warrandyte, including Warrandyte Bridge traffic and through the neighbouring Donvale and Park Orchards.

“There is also great concern for the health of the Mullum Mullum Creek and Yarra River.

“We need to consider all impacts to our communities; economically, socially and environmentally,” she said.

There is also pressure from the east.

Nillumbik groups are preparing to argue against the routes through the Green Wedge areas of Kangaroo Ground and Christmas Hills; there are serious environmental issues along these routes too.

The WCA has urged Warrandyte residents to take an active interest on this issue

Manningham City Council

Unlike other municipalities, Manningham City Council seems to be sitting on the fence when it comesto taking a position on the route the North East Link should take.

Last month Director of Assets and Engineering, Leigh Harrison, advised the Diary the “council does not currently have a formal position on the proposal”.

The council has an Integrated Transport Advisory Subcommittee (ITAC), but Mr Harrison advised “The ITAC is an advisory committee and, as such, does not formulate policy for Council’s consideration.

“The committee can agree on a view in relation to North East Link however, to date, the level of detail associated with the North East Link is too abstract to determine any concrete direction,” he said.

Their reluctance to take a position is perhaps understandable when it is considered a number of route options pass within their boundaries.

Nillumbik Shire Council

Nillumbik council officers and Councillors Karen Egan and Jane Ashton have reached agreement with NELA to hold several information sessions for local communities within the Nillumbik investigation area to talk with NELA representatives about their process, opportunities, issues and the challenges North East Link will bring so that they can use what they learn in their decision making.

The sessions are planned to be held:

  • Sunday July 23 — 9am – 12pm Eltham Town Square
  • Monday July 24 — 5pm – 8pm Nillumbik Civic Centre Greensborough
  • Saturday July 29 — 10am – 1:30pm Diamond Creek Community Centre
  • Sunday July 30 — 10am – 12:30pm Research shops

Jane Ashton said on Facebook she is aiming to organise for a meeting in Kangaroo Ground “as this is where people who care live”.

Narelle Campbell, from the No Rural Link group who have started the social media hashtag #buildthelinkbutdontsplitthewedge are opposing the road passing through the Green Wedge.

Ms Campbell thinks the sessions are “a great opportunity for our communities to engage with NELA face to face in a reasonable, evidence based, informal and passionate way”.

More formal information, engagement and feedback sessions are planned once corridors are identified and announced in August.

The North East Link Authority are not going to have an easy time ahead of them north-east Melbourne seems to find itself in a situation where most people want the link but very few want it anywhere near them.