
More power problems plague Warrandyte
by DAVID HOGG
13th March 2018
ELECTRICITY consumers in Warrandyte and North Warrandyte have experienced a number of planned and unplanned power outages in the last three months with further planned outages still to come.
Urgent work on critical pole
A spokesman from AusNet Services spokesman Hugo Armstrong has advised the Diary that a wooden power pole in the RSL grounds to the southwest of the bridge roundabout is riddled with termites and has to be replaced as a matter of urgency.
This pole carries 22kV High Voltage (HV) 3-wire cables east and west along Yarra Street and also joins the newly-installed bundled HV electrical cable which spans the river and carries power up Kangaroo Ground Road and to adjoining residential properties.
The work has been scheduled during the day on Tuesday March 20 and a power outage will affect the approximately 500 residents and businesses who were also without power on January 19 and 20 for the bridge works.
This work will be done by AusNet subcontractors.
AusNet advise that they will do their best to keep power on for the businesses in Yarra Street served by this cable, either by means of generators or by reconfiguration.
This job will be particularly tricky as the pole is in a difficult place for access, and while it is intended to keep Yarra Street open there will be complex traffic management issues and traffic delays are expected on March 20.
Further work in relation to bridge widening
To complicate matters further, as a completely separate issue the bridge contractors need further work to be done on the HV cable crossing the river and associated poles.
As a result, the same consumers will have two further daytime planned outages.
That work will be done by licensed electrical subcontractors to VicRoads.
AusNet are insisting that this latter work not be done in March but be spaced out to give long-suffering consumers some breathing space.
All affected customers will be notified in advance of these planned outages.
AusNet have asked the Diary to convey their sincere apologies to the affected customers and emphasise that they are well aware of the inconvenience caused and are doing their very best to minimise disruptions.
Later work
We announced in the May 2017 issue that the Victorian Government’s Powerline Bushfire Safety Program was completed and this had replaced 3-wire HV powerlines in North Warrandyte areas with bundled cable to reduce bushfire risks.
However, this work did not extend to replacing existing old bundled cable such as that spanning the river.
The works on January 19 and 20 replaced the old bundled cable across the river for about 5 poles up to Castle Road, but we believe that the old cable continues on past that point.
We have come across a statement from AusNet regarding the North Warrandyte power supply: “AusNet Services will replace the remaining sections of HV aerial bundled cable along this line in the coming months.
“No dates have been set as yet, but we will advise affected residents well in advance.”
Recent outages
AusNet Services released a bulletin dated January 18 entitled “Update on North Warrandyte Power Supply” which was sent by text message to all those North Warrandyte residents who had experienced recent power outages and who had a mobile phone number notified to their electricity retailer.
The bulletin lists the causes of unplanned power problems in the previous six weeks including:
- On December 9, a tree brought down overhead powerlines, which caused an extended fault and required tree clearers, traffic control and construction crews to rectify.
- On January 6, a 40 degree, extreme fire danger day, there was a burnt out HV overhead cable fault near the bridge, which caused a ‘flashover’ along the overhead wire.
- On January 11, a possum came into contact with an HV switch on Bradleys Lane, causing an outage, and as a result, the switch configuration has now been modified to prevent further possum incidents.
Additionally, on January 19 and 20 an overnight scheduled outage enabled replacement and rerouting of the HV cable across the river.
The bulletin concludes: “We are optimistic that both the reliability and safety of this part of the community have been enhanced, and you will experience better reliability in the future.”
On March 7, another possum incident caused further unplanned outages.
Mr Armstrong told the Diary “Following the possum incident on January 11 we had hoped that the modifications to the switchgear would prevent further similar incidents.
“Unfortunately, the possums had other ideas and we are now researching further solutions in attempt to minimise possum problems”.
One resident in Aton Street claims to have had a power outage every day between January 4 and 19 and has made a formal complaint to the Ombudsman.
Unplanned outages and compensation
One of the benefits of the Victorian Government’s Powerline Bushfire Safety Program completed last year was touted as being that it would improve reliability, a claim which residents are continuing to doubt.
Community frustration is growing at the continuing number of unplanned “recloser trips” being experienced almost on a weekly basis.
The recloser trip is a safety mechanism that cuts power to a localised area when there is an overload or abnormality (such as caused by possum activity) and then attempts to restore power a few seconds later.
This generally causes desktop computers and modems to reboot and causes clocks on microwaves or ovens to flash until reset.
AusNet Services are obliged to comply with a complex list of Guaranteed Service Levels (GSL) which provide for compensation if unplanned outages exceed certain targets in any calendar year.
There is no inclusion of planned outages in the GSL targets, that is those interruptions which have been notified to the consumer in advance, nor any provision for compensation for same, although sometimes ex-gratia payments are made.
The compensation starts at $30 if there are more than 24 momentary interruptions in a year, and $40 for more than 36 momentary interruptions.
Unfortunately, AusNet Services do not provide online access to the service interruption records for any property, and although details can be requested it takes a few days for a response.
The compliance with GSL targets for each residence is evaluated in February each year, and compensation payments where due are advised to the customer’s retailer in March and a credit allowed on the next bill.
However, the point at which the compensation starts is set so high that payments are — relatively speaking — rarely made, and the compensation of $30 or $40 feels like a drop in the ocean when compared with the $400+ fee per year that consumers are being charged for “service to property” before they have even started to consume any electricity.