Bridge works slip a further two months
by DAVID HOGG
14th December 2018
THE DECEMBER Bridge Update Bulletin from VicRoads is now to hand and quietly announces a further major slip to the completion date, which is now listed as “late-February”.
Considering that these works were due to be completed by the end of September and at that time slipped a further three months to “before end of 2018” it is fair to say that the project completion now slips by two months every three months.
And interestingly the contact phone numbers and email addresses for further queries have been removed from the latest bulletin.
We had all expected that the night lane closures scheduled for next week would put the final surface and line markings on the bridge and enable it to be fully opened but we now learn that this work will now not take place until late-January and not be complete until late-February.
All three lanes are now open on the bridge, with temporary barriers separating the northbound from the southbound traffic, and there has been much discussion on social media at the relative narrowness of the lanes and folk are asking why it was necessary to have two footpaths at the expense of lane width.
A single night of lane closure next week is scheduled for either Tuesday 18 or Wednesday 19 December to do some further lane marking, but obviously this will not be the finished job.
Work scheduled for the rest of December involves completing the bus stop upgrade, installing traffic signage, completing pedestrian fencing and packing up the site facilities.
Looking on the brighter side, it would seem that we do at least get all three lanes open during the upcoming fire season.